9/30/2025
- jesse4430
- Sep 30
- 1 min read
IRONWOOD - Phase 5 Construction started yesterday in the city of Ironwood. Road Closure includes Douglas Blvd at US-2 through Friday, October 3rd at 5:00 PM. The downtown business district is accessible, but the detour route was adjusted to keep large trucks away from the school zones. For large truck traffic, the detour route to downtown is from Lake Street to McLeod Ave. Lowell Street will remain closed Parking will remain available on Douglas. School bus pickups on Douglas will remain the same as this last week except for not being able to pick up at Michigan and Douglas intersection. Please use either Harding or Ridge intersection with Douglas instead for this one week. All underground pipe work is scheduled to be completed by Friday, October 3rd. Concrete curb, sidewalk and road building work will continue throughout October.